I-405 Sepulveda Pass Widening Project:
Church Lane is now open. As of this afternoon Church Lane has been opened up to all traffic.
Work will be commencing on widening the Montana undercrossing. Work is scheduled to begin Friday November 12th. This entails abutment removals on November 12th and November 15th. Work hours will be from 9 PM to 6 AM.
From November 16th - the 18th there only will be Westbound access to at the Montana undercrossing for temp storm drain relocation. Again this will occur between 9 Pm - 6 AM.
Full closure of the undercrossing at Montana is anticipated to start on Dec. 1st fro approximately one month at night between 9 PM - 6 AM.
Eastbound Montana traffic detours will take drivers up Church Lane to Sepulveda and back to Montana.
Westbound Montana traffic will be detoured up Sepulveda to Church Lane.
During this time Sepulveda will be narrowed to one lane going in each direction.
Plan on there being ramp closures on the Montana off ramp. When these closures occur they will be between the hours of 7 PM and 6 AM.
Montana Bridge reconstruction and widening is expected to last approximately eight months.
For up to date information:
Email: I405 @metro.net
Website: www.metro.net/I405
Twitter: http://twitter.com/I_405
Facebook: www.facebook.com/405project
Nixle: nixle.com
Project Hotline: 213.922.3665
No comments:
Post a Comment